top of page

Construction Progress

After the ceremonial Groundbreaking on June 20, 2019, ground preparations, demolitions, and excavation began in earnest.  We note that The Ursuline School seal was carefully removed from the floor of the lobby and preserved in the staging area. The JB Commons pavers and the senior path were also safeguarded.

 

The first concrete was poured on October 1, 2019.  Foundation walls were then formed. The second concrete pour was on October 28, 2019.  The next exciting step was the steel beams going up, before Thanksgiving. The steel decking was mounted. On January 14, 2020 the cement floor was poured and cement steps were formed; later that month the roof trusses were installed. In February 2020, the roof was put in place and the new spaces began to be enclosed.

In March 2020, we closed the campus in line with COVID-19 directives and we transitioned to distance learning. The absence of students presented an advantage in terms of this project. The construction work originally scheduled for summer was accelerated to begin in April 2020. Although struggling with delays in manufacturing and the effects of the virus on many trades, the work that could be expedited was begun.

Over the summer of 2020, as deliveries of materials resumed, the interior took shape. Windows, flooring, and cabinetry were installed. The green roof was installed in early September 2020. That vegetation absorbs rainwater, purifies the air, and reduces the ambient temperature. The Innovation Hub was made ready for the placement of the laser cutters, microcontrollers, and writable walls for students to use as they create and invent. 

 

On September 13, 2020, Msgr. Keane blessed the new learning and social spaces. The Christina Jun Murphy '22 Commons was completed in time for the beginning of classes in September 2020. Tremendous progress took place in the other spaces as well. Soon, students were enjoying the Kulsar – McCarthy Lobby and Welcome Center, where certain mornings the choirs performed. Walking along the Nasti Family Corridor, students enter the High-Tech Media Conference Center for Global Scholar presentations, moot court, and Model UN in this seminar-style room.  The Maalouf Family Collaborative Workspace is used for faculty meetings or project work by students. The Administrative wing  is completed and features modern offices including the Mary Louise & William McCarthy Main Office.  The iHub was officially opened on January 28, 2021 and the doors to the lobby were formally opened on March 9, 2021.  Admissions is conducted virtually for  now out of the Ann Clemente Admissions Suite that includes the Verni Family Conference Room. The expanded bookstore is popular. We are happy to see the outside landscaping take shape as the construction nears completion.

Please enjoy the PHOTOS below and

the May 2020 VIDEO that shows the exciting progress to that point!

Please click on the image below to watch the video or Click HERE.

Construction video May 2020 play button
  1. View of part of the Murphy Commons
  2. Inside look at the iHub
  3. Interior office takes shape
  4. Construction of the Admin wing
  5. View of where JB Commons will be re-installed
  6. The green roof almost ready for vegetation
  7. Construction on the iHub roof
  8. More work on the roof
  9. A view of the lobby roof installed
  10. Roof over the iHub
  11. Inside look as new hallway built
  12. New spaces join the existing building
  13. Inside look at the iHub
  14. Cast your eyes up to the new lobby roof
  15. Sides of the lobby are formed
  16. View from North Ave of the new lobby
  17. View from the circle of the lobby exterior
  18. Roof over the lobby
  19. Roofing the lobby
  20. Framing of roof
  21. Frame of peaked roof
  22. Roof trusses
  23. Cement steps
  24. Cement steps are prepared
  25. Cement floors are smooth
  26. Ursuline markings on beam
  27. Smooth cement floors
  28. Setting cement floors
  29. Leveling with rakes
  30. Cement floors are leveled
  31. Careful spreading of cement
  32. Rakes level the cement floors
  33. Team work
  34. Cement mixer back on campus
  35. Cement floors are poured
  36. Steel decking top view
  37. Steel decking
  38. Steel decking underneath
  39. Steel decking
  40. Steel goes up
  41. Foundation walls, lobby
  42. Foundation walls of the iHub
  43. Second concrete pour
  44. Second concrete pour, foundation
  45. Foundation walls, photo by Chris Pope
  46. Construction aerial view by Chris Pope
  47. Forming walls
  48. Forming foundation walls
  49. 65 yards of concrete poured throughout our site
  50. Concrete poured for the new lobby
  51. Street side of iHub perimeter with concrete poured
  52. Floating with hand tool to compact the concrete
  53. Screeding with wooden plank & floating to create a flat surface
  54. Using vibrator for footing concrete
  55. Spreading concrete with shovels, rakes
  56. Concrete pouring into wooden form
  57. Pouring concrete & vibrating for footing
  58. Aerial view of iHub concrete poured
  59. Pouring first concrete, iHub form
  60. Cement truck, up close
  61. Concrete pump & cement truck
  62. Concrete pump; time for concrete!
  63. Wooden form of iHub
  64. Outline of new perimeter takes shape
  65. Close up of forming process
  66. Aerial view of forming process
  67. Excavation of perimeter
  68. Construction iHub inside 5.27.20.jpeg
  69. Excavation of perimeter wall and boulder removal
  70. View after demolition of retaining wall
  71. Demolition of retaining wall

  72. Excavation begins.
  73. The old lobby has been removed.

  74. The pillars of the old lobby.
  75. The school seal has been set aside carefully.

  76. Preparing to remove the seal in the old lobby floor and safeguard it.
  77. Digging outside the old lobby.
  78. Lobby demolition, aerial view.
  79. Lobby demolition commences.

  80. Paths are made for the construction vehicles.
  81. Fencing goes up and we are on our way.

TUS_Campaign_LOGO_just Rectangle.jpg

Contact Us

Thanks for submitting!

THE URSULINE SCHOOL | 1354 North Avenue, New Rochelle NY 10804-2192 | 914-636-3950

www.ursulinenewrochelle.org

© 2023 by ITG. Proudly created with Wix.com

bottom of page